Two Mozambique Projects Undertaken by the Group Corporation finish
In July 20th the completion ceremony of Mozambique Quelimane water supply system and Licuari water disposal installation undertaken by the Eleventh Bureau held in Nikodala Water Supply Center. Mozambique President Mr.Armando Emilio Guebuza attended the ceremony and and cut the ribbon for project completion unveiling.
Mozambique water supply project started in November 2004, and achieved water supply for the whole main line in November 6, 2006; Mozambique Licuari water disposal installation started in January 16, 2006, the main part concrete finished in June 30 , 2007, and the first trial generation of the system succeeded in July 19.